Written question WQ83609
- Asked by
- Peredur Owen GriffithsPlaid
- To be answered by
- Minister for Climate Change
- Tabled
- Due
- Answered
- Time to answer
- 6 days
Question
Will the Minister confirm the date when the junction to the A465 at Brynmawr is expected to reopen?
Answer
Answered by Deputy Minister for Climate Change
The A465 section 2 project remains on target for completion later this year, though additional repair works to Clydach Viaduct have resulted in some delays. The Brynmawr off-slip will be re-opened at the earliest opportunity following the traffic switch to the upper level in August last year.
We are grateful for the patience of road users and those living and working in the area whilst final construction works are completed on this tremendous engineering challenge which will bring further benefits to the Heads of the Valleys communities.