Question
Will the Minister confirm how many schemes have yet to be completed under the coastal risk management programme?
Answer
Answered by Minister for Climate Change
There are five coastal risk management programme schemes currently in construction. Two more schemes were awarded Welsh Government grant funding in December 2022.
The remaining six coastal risk management programme schemes are at full business case phase with various schedules to start construction before March 2024 subject to the successful completion of business cases, match funding availability and relevant consents/permissions.