Question
Will the Minister provide a breakdown of the £9 million spent on the project to remove the two roundabouts on the A55?
Answer
Answered by Deputy Minister for Climate Change
The below table provides a breakdown of the costs.
Description
Cost
Option selection, preferred options development, preparation of Environmental Statement and draft Orders.
£5,335,000.00
Surveys including environmental, traffic and ground investigation.
£925,000.00
Statutory process including publishing draft Orders & Environmental Statement and prepare for Public Local Inquiry
£1,160,000.00
Technical, environmental and commercial advisors’ fees
£1,600,000.00
Total
£9,020,000.00