Have all the required new trains for the core valley lines been manufactured, and are they in Wales ready for use?
Answer
Answered by Deputy Minister for Climate Change
48 trains for the Core Valley Lines have been manufactured and are in Wales. Four trains have been manufactured but are not yet in Wales. 19 trains are still being manufactured.