Question
What was the initial completion date given by the contractors currently undertaking the flagpole replacement work outside Tŷ Hywel?
Answer
Answered by Senedd Commission
Llywydd on behalf of the Senedd Commission:
The initial complete date given by the contractors currently undertaking the flagpole replacement work outside Tŷ Hywel was March 24. Works to date have been completed to programme and we anticipate that this completion date will be met.