Will the Minister provide an update on when the construction of the Redstone / Llandewi Velfrey bypass on the A40 will commence?
Ateb
Atebwyd gan Deputy Minister for Climate Change
Following the letter of intent issued by Welsh Government to Alun Griffiths Contractors, detailed design work is underway and site works will start week commencing 21 June 2021.