Cwestiwn ysgrifenedig WQ92100
- Gofynnwyd gan
- Andrew RT DaviesCeidwadwyr
- I'w ateb gan
- Minister for Climate Change
- Cyflwynwyd
- Dyddiad ateb
- Atebwyd
- Amser i'w ateb
- 7 diwrnod
Cwestiwn
Mae'r cwestiwn a'r ateb yn Saesneg gan nad oes fersiwn Gymraeg ar gael.
Will the Minister outline why there was a delay in the introduction of the Warm Homes Programme?
Ateb
Atebwyd gan Minister for Climate Change
The new Warm Homes Programme is worth over £200m and we needed to ensure we are getting the maximum value for public money.
Given the complexity of the services being procured to deliver this scheme, extra assurance steps in the evaluation process were required, resulting in slippage to the procurement timeline. Pre-emptive action was taken to extend the current Nest contract to the end of March 2024, thereby continuing to help low-income households over the winter.