Cwestiwn
Mae'r cwestiwn a'r ateb yn Saesneg gan nad oes fersiwn Gymraeg ar gael.
What is the anticipated cost of the upkeep and maintenance of the overhead wiring on the new Transport for Wales metro lines?
Ateb
Atebwyd gan Cabinet Secretary for North Wales and Transport
Once the overhead line equipment is fully energised and operational, Transport for Wales anticipate a full-year maintenance cost to be of c. £600k (in 2023/24 prices).