Cwestiwn ysgrifenedig WQ94270
- Gofynnwyd gan
- Peredur Owen GriffithsPlaid
- I'w ateb gan
- Cabinet Secretary for Transport and North Wales
- Cyflwynwyd
- Dyddiad ateb
- Atebwyd
- Amser i'w ateb
- 7 diwrnod
Cwestiwn
Mae'r cwestiwn a'r ateb yn Saesneg gan nad oes fersiwn Gymraeg ar gael.
What proportion of rail journeys in Wales are currently being undertaken by new trains, specifically Class 197, Class 230, Class 231 and Class 756 trains?
Ateb
Atebwyd gan Cabinet Secretary for Transport and North Wales
The completion of Transport for Wales’ New Fleet Programme was delayed due to manufacturing issues and delays in the Core Valley Lines Transformation Programme.
Further to WQ89224, Transport for Wales have made significant progress on accepting and introducing new fleet in the last 12 months. From the December 2024 Timetable Change TfW will be operating 60% of their services on new fleet.