Cwestiwn ysgrifenedig WQ95836
- Gofynnwyd gan
- Gareth DaviesCeidwadwyr
- I'w ateb gan
- Cabinet Secretary for Transport and North Wales
- Cyflwynwyd
- Dyddiad ateb
- Atebwyd
- Amser i'w ateb
- 6 diwrnod
Cwestiwn
Mae'r cwestiwn a'r ateb yn Saesneg gan nad oes fersiwn Gymraeg ar gael.
Will the Cabinet Secretary provide a timescale for the replacement of Llanerch Bridge?
Ateb
Atebwyd gan Cabinet Secretary for Transport and North Wales
Denbighshire County Council have received £750,000 from our Resilient Roads Fund in 2024-25 to take forward design work on a replacement for the bridge this financial year. The detailed design stage of the project has recently been completed and the outcome of this process is currently being considered, with Denbighshire County Council also engaging with the directly affected statutory undertakers. As Denbighshire County Council are currently considering the detailed design, I am unable to confirm a timescale for the completion of the works at this stage.